UBBL 2016 – Chapter 2 MCQ Question Bank (Set 4 & Set 5)
Set 4 – 40 MCQs (CAF, NOCs, Plans & Fees)
Attempt all questions and then click “Check Set 4 Answers”. You will see your score and per-question red/green feedback.
-
Q1. “Common Application Form (CAF)” primarily combines:
-
Q2. COCCRF is mainly used for:
-
Q3. Which of the following is NOT a typical enclosure with CAF?
-
Q4. In UBBL 2016, which communication mode is preferred for all building permission processes?
-
Q5. Minor addition/alteration without permit is allowed when:
-
Q6. Which of the following requires a building permit?
-
Q7. Sunshade up to 0.75 m width without permit is allowed only if:
-
Q8. Internal partition walls can be added/removed without building permit if:
-
Q9. Maximum area for porta cabin allowed without building permit in certain large plots is:
-
Q10. Erection of lifts in existing buildings without permit applies to:
-
Q11. Which is NOT included under “services plan” accompanying the building plan?
-
Q12. Key plan scale recommended in UBBL 2016 is:
-
Q13. All drawings under UBBL 2016 are to be prepared in:
-
Q14. In recommended colouring, existing work to be retained is generally shown as:
-
Q15. Proposed new work in plans is shown with:
-
Q16. Proposed drains and water supply lines are indicated with:
-
Q17. For site areas up to 1000 sqm, minimum recommended site plan scale is:
-
Q18. Which of these is NOT a purpose of giving standard sheet sizes (A0–A4)?
-
Q19. Common Application Form helps mainly to:
-
Q20. Which document proves leasehold title during CAF submission?
-
Q21. Which of the following satisfies the requirement of proving ownership in freehold property?
-
Q22. Assertion (A): CAF includes tentative dates of start and completion of work.
Reason (R): This helps automatic intimation to Labour Department regarding duration of construction. -
Q23. Structural safety declaration in CAF is given by:
-
Q24. Notice for building permit is generally deemed invalid if:
-
Q25. Building permit fee is normally charged on:
-
Q26. For storage/warehouse buildings, permit fee per sqm is:
-
Q27. Revision of building plans attracts:
-
Q28. Land-subdivision/layout approval fee is primarily based on:
-
Q29. Resubmission of plan after rejection (up to three times) generally requires:
-
Q30. Assertion (A): External NOCs are fully independent of building permit process.
Reason (R): Building permit is issued only by municipal authority and does not depend on external agencies. -
Q31. External agencies like DFS, DPCC, DUAC, AAI share their decision on NOC through:
-
Q32. If an external NOC agency does not respond within stipulated time, normally:
-
Q33. Reasoning: Colour-Coded Zonal Maps (CCZM) are mandated so that:
-
Q34. The risk-based approach in Chapter 2 and 3 mainly affects:
-
Q35. For very low and low risk buildings, sanctioning authority generally relies on:
-
Q36. For moderate and high risk buildings, SA:
-
Q37. Which statement is TRUE about deemed sanction of building plans?
-
Q38. In case of partial compliance of objections on building plan:
-
Q39. Notice for demolition under UBBL 2016:
-
Q40. Building plan approvals under UBBL 2016 are expected to be:
Show Set 4 Answer Key
Set 5 – 40 MCQs (Validity, OCC, Regularisation & GRC)
Attempt all questions and then click “Check Set 5 Answers”.
-
Q1. Maximum validity of a building permit from the date of sanction is:
-
Q2. Minimum requirement to keep permit valid is that construction should commence within:
-
Q3. After expiry of building permit, further construction is:
-
Q4. Application for OCC must be filed within:
-
Q5. Revalidation of building permit can be granted:
-
Q6. Ownership documents at time of revalidation are needed particularly if:
-
Q7. Plinth inspection for very low/low risk buildings is primarily done by:
-
Q8. Plinth inspection for moderate/high risk buildings is carried out by:
-
Q9. Time limit for sanctioning authority to carry out plinth inspection after C-1 is received:
-
Q10. If plinth inspection is not done within prescribed period:
-
Q11. OCC is normally applied after:
-
Q12. For OCC, minimum conditions include:
-
Q13. Partial OCC usually can be given:
-
Q14. Partial OCC does NOT:
-
Q15. If external agencies do not give their NOC for OCC within stipulated time:
-
Q16. Assertion (A): Time limit for OCC decision starts from date of submission of COCCRF.
Reason (R): If shortcomings are pointed out, and owner resubmits compliance, countdown restarts from last compliance date. -
Q17. If owner fails to remove OCC shortcomings within 15 days:
-
Q18. Deemed OCC arises when:
-
Q19. Deemed OCC is actually released after:
-
Q20. Deemed OCC does NOT:
-
Q21. Regularisation under 2.8 applies to:
-
Q22. Regularisation is granted through:
-
Q23. Under 2.9.1, building permit can be revoked if:
-
Q24. Demolition of unauthorised construction beyond permissible limits is done:
-
Q25. Assertion (A): Professionals who misrepresent facts can be de-listed under UBBL 2016.
Reason (R): De-listing and publication of names act as deterrent and promote ethical practice. -
Q26. De-listing details of defaulting professionals are to be:
-
Q27. In case of architect’s misconduct, SA may inform:
-
Q28. Latent defects liability typically covers:
-
Q29. Decennial professional liability insurance normally covers a period of:
-
Q30. Plots for which latent defects liability applies are:
-
Q31. Parties covered under latent defects liability include all, EXCEPT:
-
Q32. Owner’s responsibility under 2.11 is:
-
Q33. Pre-Code Building Permit refers to:
-
Q34. Grievance Redressal Committee under UBBL 2016 deals with:
-
Q35. Decisions of Grievance Redressal Committee regarding interpretation are:
-
Q36. As per UBBL 2016, who is discouraged from pursuing cases in SA offices?
-
Q37. UBBL 2016 encourages owners to:
-
Q38. Which statement best describes the philosophy of Chapter 2 (read with Chapters 3 & 4)?
-
Q39. Assertion (A): Building approvals are now risk-based and time-bound.
Reason (R): Different categories of buildings face different levels of scrutiny and inspection in proportion to their risk. -
Q40. Overall, what remains the ultimate legal obligation of the owner even after getting sanction and OCC?